Monday, November 28, 2011

Project Schedule Network Diagram

The project schedule network diagram is a visual representation of the activities in a project and their inter-dependency. There are two common approaches to build a network diagram. The first approach is the Precedence Diagramming Method (PDM) which is also called Activity-On-Node (AON) (Figure 1).


Figure 1  Precedence Diagramming Method Example


In this network diagram, the activities are represented by boxes (node) and the logical relationships between the activities are presented by arrows. PDM allows the use of the four types of relationships that are finish-to-start (FS), finish-to-finish (FF), start-to-start (SS), and start-to-finish (SF). Figure 2 shows the representation of these different relationships. This approach is the most common one and supported by major scheduling software such as Primavera and MS Project. 


Figure 2 Relationship Representation in PDM

The second type is the Activity-On-Arrow (AOA) as shown in Figure 3. In this network diagram, the activities are represented by an arrow and connected by nodes. The nodes represent an event which could be the start or completion of an activity. Finish-to-start is the only relationship that can be used to express the dependency between activities when using the AOA approach. Sometimes it is necessary to use a dummy activity, which is an activity that has no time, to maintain the logical relationships in an AOA network. 


Figure 3 Activity On Arrow Example




If you have any questions, please do not hesitate to ask.
In future posts I will talk about the logical relationships between activities, how to construct an AOA network, and finding the critical path.